01
BPDB.
Augmentation and execution of 132/33 kv
Grid Sub-Station including modification of
control room building at Kishorgonj and
jamalpur under AGS-Scheme.
7,90,610.00
(1987-1991)
02
BPDB.
Augmentation and execution of Grid Sub-
Station modification of control room
building at Thakurgaon, Purbasadipura and
saidpur 132/33 kv Grid Sub- Station under
AGS Division –IV, BPDB, Rangpur.
30,48,648.00
03
BPDB.
Augmentation and extension of Grid sub-
station modification of control room
building at Mymensing under AGS. Scheme
of BPDB
1078,915.00
1991
04
BSCIC
Construction of Administrative and
resdential Building at BSCIC Industrial
Estate, Hobigonj,, BSCIC, Chitagong.
11,60,672.84
1992
05
BSCIC
Construction of Administrative and
resdential Building at BSCIC Industrial
Estate, Kishorgonj, BSCIC.
13,85,960.00
1994
06
BSCIC
Construction of herring bone bond and
carpeting road at BSCIC Industrial Estate,
Khadimnagar. Sylhet.
38,53,723.97
1995
07
BSCIC,
Construction of herring bone bond road and
drain at BSCIC Industrial Estate,
Sholoshahor.
25,25,000.00
08
MES
Extention of 2Xwings at port of Academey
Building at BNA, CTG.
36,39,398.00
1995
09
Mohakhali PWD
Division, Dhaka.
Construction of permanent Hajj camp at
Ashkona, Uttara, Dhaka. Group No-VI
(Block-B, 5 Storied) including 140 ft. Minar
with Gammon Bangladesh Ltd.
8,40,72,664.80
1997
10
Mohakhali PWD
Division, Dhaka.
Site improvement with earth in the
permanent Hajj camp at Ashkona, Uttara
Dhaka with Gammon (Bangladesh) Ltd.
68,75,982.00
1996
11
Mohakhali PWD
Division, Dhaka.
Construction of permanent Hajj camp at
Ashkona, Uttara, Dhaka. Group No-VI
(Block-B, 5 Storied) including 140 ft.
Minar. Sub Head:Internal Eletrification
Works.
11,75,975.00
1998
12
Dhaka PWD
Division-4
Construction of covered Gang way
Connecting Supreme Court Building with
old High Court Building at Dhaka.
51,38,143.00
1999
13
City PWD
Division
Construction of 2 nd &3 rd floor over the
existing 1 st floor of 40 cell at Dhaka.
52,00,000.00
1999
14
City PWD
Division
Construction of Training Center (SEMI
PUCCA) at jamdani Industrial Estate,
Narayangonj.
7,23,900.00
1999
15
City PWD
Division.
Construction of SSF Guard room at Prime
Minister office at Dhaka.
2,32,810.00
1999
16
Facilities Dept.
Construction of 3(Stroied) Academic
Building at Bandorban. Chittagong under
facilities Dept.
31,49,000.00
2002
17
City PWD
Division.
Construction of 6(six) Storied Mobilization
Building at Osmani Uddayan, Dhaka. with
Gammon (Bd) Ltd.
2,90,31,815.70
2004
18
Sher-e-bangla
Nagaor Division-2
Construction of SARC Meteorological
Research Center (SMRC) Building at
Agargaon, Dhaka.
2,45,99,399.00
2005
19
PWD Resource
Division,
CONSTRUCTION OF 6 STORIED
BUILDING OF 1800 (10 UNITS) FLATS AT
H # 25-26, R # 8, DHANMONDI R/A,
DHAKA now at Alenbari PWD Resource
compound under PWD Resource Division,
Alenbari, Dhaka. (INCLUDING SANITARY,
WATERSUPPLY,INTERNAL
ELECTRIFICATION ETC) (LOT NO-2)
2,38,25,059.00
2007
20
PWD Resource
Division,
CONSTRUCTION OF 6 STORIED
BUILDING OF 1800 (10 UNITS) FLATS AT
H # 25-26, R # 8, DHANMONDI R/A,
DHAKA now at Alenbari PWD Resource
compound under PWD Resource Division,
Alenbari, Dhaka. (INCLUDING SANITARY,
WATER SUPPLY, INTERNAL
ELECTRIFICATION ETC) (LOT NO-3)
2,20,84,013.00
2008
21
PWD Resource
Division,
CONSTRUCTION OF 6 STORIED
BUILDING OF 1800 (10 UNITS) FLATS AT
H # 25-26, R # 8, DHANMONDI R/A,
DHAKA now at Alenbari PWD Resource
compound under PWD Resource Division,
Alenbari, Dhaka. Sub-Head: Earth filling
8,36,936.00
2008
22
City PWD
Division.
Construction of 2 (Two) Storied Magzine
Building at Ousmani Uddyan Bangladesh Police
Control Room Project. Abdul Gani Road,
Dhaka.
36,80,424.00
2007
23
City PWD
Division.
Road carpeting work at Ousmani Uddyan
Bangladesh Police Control Room Project.
Abdul Gani Road, Dhaka.
16,45,293.00
2008
24
PWD Resource
Division
CONSTRUCTION OF 6 STORIED
BUILDING OF 1800 (10 UNITS) FLATS AT
H # 25-26, R # 8, DHANMONDI R/A,
DHAKA now at Alenbari PWD Resource
compound under PWD Resource Division,
Alenbari, Dhaka. Sub-Head: Pre-cast file
Driving at lot-3.
17,98,666.58
2008
25
PWD Resource
Division
CONSTRUCTION OF Sub-Station at Alenbari
PWD Resource compound under PWD
Resource Division, Alenbari, Dhaka. Sub-Head:
Electrical Sub-Station.
12.12.432.00
2008
26
Construction of seven Storied Apartment
Building at Holding no 1045/1 Purba
Monipur, Mirpur, Dhaka.
8,50,00,000.00
2008
27
Construction of seven Storied Apartment
Building at Holding no T-23, Noor jahan
road, Mohamedpur, Dhaka.
2,50,00,000.00
2008
28
Construction of seven Storied Apartment
Building at Holding no U-04, Noor jahan
road, Mohamedpur, Dhaka.
2,50,00,000.00
2008
29
Construction of Nine Storied Apartment
Building with basement car parking at
Holding no 123,116 , Road no -13/A,
Dhanmondi, Dhaka-1209.
9,00,00,000.00
2009
30
Augmentation and Execution of 132/33 K.V Grid Sub-Station at Ishurdi,
Rangpur, Bogra and sylhet Under AGS Scheme of BPDB, Dhaka.
31
Construction of Switching station at Shahjibazer power station under P & D
Circle BPDB, Dhaka
32
Augmentation and execution of Grid Sub-station including modification of control
room Building at comilla & Feni under AGS Scheme of BPDB.
33
Installation of 132/33KV, 10/13.5 MVA Transformer and other protection
equipment’s at polashbari 132 KV Grid Sub-Station Under AGS, Division –iv,
BPDB , Rangpur.
34
Installation and commissioning of 132KV SF-6 Breaker and other equipment’s at
kulshi Grid sub-station, Chittagong
35
Emergency Work at polasBari 132 KV. Grid –Sub-Station for repair, ,Installation
and Commissioning of 132KV 10/13.5 MVA Burning Transformer. Under AGS
Division-IV, BPDB,Rangpur
36
Installation of 10/12.5 MVA 132/33 KV Transformer and other Equipments for
augmentation of srimongal Grid –sub-Station under AGS Scheme Of BPDB.
37
Installation and Commissioning of 33KV.MOCB and other equipments including
control and signal panels at Bhairab Bazer,33KV Switching Station
38
Augmentation and execution of Grid Sub- Station of Bogra , Polashbari and
Rangpur under AGS Scheme of BPDB, Dhaka.
39
Installation and Commissiong of 33KV Switching station at Tangail Under Central
Zone,PBDB, Mymenshing.
40
Construction of 1x6 MRD,OR’SQuater (Multistorieed building) including road ,
Drain ect at Rangpur cantonment, Rangpur under MES.
41
Consultancy services of srimongol and Fenchugonj 132/33 KV. Grid-Sub-Station
Under AGS Scheme of BPDB.Dhaka.